Restoring a 37,000 sq ft PennDOT Maintenance Facility in Indiana County, PA

An aged TPO roof over a working state highway shop. Restored in place with a fabric-reinforced acrylic system — no tear-off, and no interruption to District operations.

OwnerPennsylvania Department of Transportation — Engineering District 10
LocationIndiana County, Pennsylvania
BuildingState mechanical / maintenance shop, 37,000 sq ft
Roof we foundAged TPO single-ply membrane
System installedFabric-reinforced acrylic basecoat + polyurethane-modified acrylic topcoat
Tear-offNone
OperationsNo interruption to District operations
Wage termsPennsylvania Prevailing Wage, certified payroll
Drone aerial of the restored PennDOT District 10 roofs

What We Found

A 37,000 sq ft TPO roof that had reached the age where membranes start to fail — over a shop that keeps District 10’s highway equipment running.

That second part shaped everything. A District maintenance shop does not have a convenient month in which to be roofless. Equipment is in the bays, crews are working underneath, and the building is needed through every season. A tear-off would have meant opening the roof over that work, phase by phase, and exposing it to weather each time.

The question was not whether the roof needed work. It was whether the existing roof could carry a restoration system — or whether it had to come off.

PennDOT District 10 aged roof membrane before restoration

What We Did

We restored it in place. The existing TPO stayed on the building and became the base for a new, seamless system:

  1. Surface preparation of the aged TPO to accept the new system.
  2. Fabric-reinforced acrylic basecoat — reinforcing fabric embedded in the basecoat, building a continuous reinforced membrane across the field and the details.
  3. Polyurethane-modified acrylic topcoat over the reinforced base.

Because nothing came off, the building was never open to weather, and there was no demolition phase to work around. The work ran under Pennsylvania Prevailing Wage, with certified payroll.

It is the same system we used on Cleveland Brothers’ 60,000 sq ft Caterpillar machine shop — over aged black EPDM there, over aged TPO here.

→ Fabric-Reinforced Roof Systems

Seams and a penetration detailed in white basecoat on the PennDOT District 10 roof

The Result

  • A restored 37,000 sq ft roof with a new, seamless, reinforced surface.
  • No tear-off — and none of the landfill, exposure or insulation-upgrade cost a tear-off to the deck brings with it.
  • No interruption to District operations. The shop kept working throughout.

Why it matters beyond this building: together with Cleveland Brothers, it shows one restoration system working over both EPDM and TPO — the two membranes most aging commercial roofs in Western Pennsylvania are made of. The system is chosen for the condition of the roof, not for the brand of membrane somebody installed years ago.

PennDOT District 10 fabric-reinforced roof, wide view showing scale

Is Your Roof a Candidate for the Same Approach?

Usually, if three things are true:

  • The insulation underneath is dry. An infrared moisture survey shows this across the whole roof.
  • The deck is sound.
  • The membrane is aged but still a continuous surface that a reinforced system can bond to and bridge.

If those hold, restoration typically costs far less than replacement. If they do not, we will tell you that too.

→ Commercial Roof Coatings · Roof Inspections

Public and Institutional Owners

Public buildings carry rules private ones do not: prevailing wage, certified payroll, documented process, and operations that cannot stop. This project ran under all of them.

📞 412-888-0283 · Monday–Friday, 7 a.m.–5 p.m. · 1410 Wayne Avenue, Suite D, Indiana, PA 15701

Frequently Asked Questions

Can a fabric-reinforced coating go over an old TPO roof?

Yes, when the insulation underneath is dry and the deck is sound. On PennDOT District 10 we restored 37,000 sq ft of aged TPO with a fabric-reinforced acrylic basecoat and a polyurethane-modified acrylic topcoat, without tearing it off.

Did the building have to close during the work?

No. The work was done with no interruption to District operations. With no demolition phase, the building was never open to weather.

Do you do prevailing wage work?

Yes. This project ran under Pennsylvania Prevailing Wage with certified payroll.

What is the difference between this and a roof replacement?

A replacement tears the roof off to the deck and rebuilds it, which can also trigger an insulation upgrade under the energy code. A restoration keeps the existing roof in place and builds a new, reinforced surface on top — when the roof qualifies, at far less than replacement.